Training Rollout Initiative and Plan





Project Start:
Project Finish:
Thu 3/4/04
Mon 10/11/04


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Training Rollout Initiative and Plan (TRIP)
157.5 daysThu 3/4/04Mon 10/11/04 0%
2
TRIP - Stage 1 - Project Planning
19 daysThu 3/4/04Tue 3/30/04 0%
3
Define project objectives and describe mission statement
2 daysThu 3/4/04Fri 3/5/04 0%
4
Ensure total participation by training team support staff
1 dayThu 3/4/04Thu 3/4/04 0%
5
Identify Departments or End-User Community to be Trained
7 daysFri 3/5/04Mon 3/15/04 0%
6
Create list of target departments
1 dayMon 3/8/04Mon 3/8/04 0%
7
Perform departmental training needs analysis
7 daysFri 3/5/04Mon 3/15/04 0%
8
Compile results and present findings to training coordinator
2 daysWed 3/10/04Thu 3/11/04 0%
9
Prioritize training delivery according to critical need
2 daysFri 3/12/04Mon 3/15/04 0%
10
Inform department heads of the training initiative
2 daysTue 3/9/04Wed 3/10/04 0%
11
Determine if training can be done in-house or outsourced
1.5 daysTue 3/9/04Wed 3/10/04 0%
12
Seek Input from Training Vendor
11 daysWed 3/10/04Thu 3/25/04 0%
13
Define vendor deliverables - can they meet our needs?
1 dayWed 3/10/04Thu 3/11/04 0%
14
Obtain vendor commitment to training rollout schedule
3 daysThu 3/11/04Tue 3/16/04 0%
15
Review and customize training material
7 daysTue 3/16/04Thu 3/25/04 0%
16
Obtain approval for purchase orders to cover vendor invoices
2 daysTue 3/16/04Thu 3/18/04 0%
17
Perform End-User Skill Assessment
11 daysTue 3/16/04Tue 3/30/04 0%
18
Create a list of training recipients by department
2 daysTue 3/16/04Wed 3/17/04 0%
19
Send skill assessment forms to department heads
2 daysThu 3/18/04Fri 3/19/04 0%
20
Collect and compile results by department
5 daysMon 3/22/04Fri 3/26/04 0%
21
Initiate end-user placement matrix
3 daysThu 3/25/04Mon 3/29/04 0%
22
Finalize project budget
2 daysMon 3/29/04Tue 3/30/04 0%
23
Stage 1 - TRIP - End project initiation
0 daysTue 3/30/04Tue 3/30/04 0%
24
TRIP - Stage 2 - Project Commencement
14 daysTue 3/30/04Fri 4/16/04 0%
25
Prepare Rollout Schedule and Create Awareness
12 daysTue 3/30/04Wed 4/14/04 0%
26
Determine course dates, start and end times, and locations
3 daysTue 3/30/04Thu 4/1/04 0%
27
Post course outlines and schedule on corporate intranet
1 dayFri 4/2/04Mon 4/5/04 0%
28
Establish support through help desk for post-training questions
1 dayFri 4/2/04Fri 4/2/04 0%
29
Reserve training rooms
1 dayFri 4/2/04Fri 4/2/04 0%
30
Coordinate with information technology team for optimal workstation and equipment performance
1 dayMon 4/5/04Tue 4/6/04 0%
31
Order training manuals and necessary material
7 daysFri 4/2/04Mon 4/12/04 0%
32
Marketing Strategy
9 daysFri 4/2/04Wed 4/14/04 0%
33
Order promotional material
7 daysFri 4/2/04Mon 4/12/04 0%
34
Create posters and place them in high-traffic areas
4 daysFri 4/9/04Wed 4/14/04 0%
35
E-mail invitation to participants
1 dayFri 4/9/04Fri 4/9/04 0%
36
Arrange for catering of meals and refreshments
1 dayMon 4/12/04Mon 4/12/04 0%
37
Training Sessions Registration
5 daysFri 4/9/04Thu 4/15/04 0%
38
Enroll users who registered via corporate intranet
2 daysFri 4/9/04Mon 4/12/04 0%
39
Send out confirmations to these registration
1 dayTue 4/13/04Tue 4/13/04 0%
40
Send out prework requirements
2 daysFri 4/9/04Mon 4/12/04 0%
41
Monitor cancellations and late requests for training
1 dayThu 4/15/04Thu 4/15/04 0%
42
Schedule Instructors
3 daysMon 4/5/04Thu 4/8/04 0%
43
In-house instructors
1 dayMon 4/5/04Tue 4/6/04 0%
44
Outsourced instructors
3 daysMon 4/5/04Thu 4/8/04 0%
45
Courseware Evaluations
3 daysWed 4/7/04Mon 4/12/04 0%
46
Reuse or build an end-user course evaluation form (online or paper)
2 daysWed 4/7/04Fri 4/9/04 0%
47
Reuse or build an special feedback form for instructors
2 daysThu 4/8/04Mon 4/12/04 0%
48
Stage 2 - TRIP - End project commencement
0 daysFri 4/16/04Fri 4/16/04 0%
49
TRIP - Stage 3 - Project Implementation and Control
13.5 daysWed 4/21/04Mon 5/10/04 0%
50
Conduct training and track attendance
10 daysWed 4/21/04Tue 5/4/04 0%
51
Daily Conference Call (Hold Daily Call to Address Issues)
9.25 daysWed 4/21/04Tue 5/4/04 0%
52
Call 1
1 hrWed 4/21/04Wed 4/21/04 0%
53
Call 2
1 hrThu 4/22/04Thu 4/22/04 0%
54
Call 3
1 hrFri 4/23/04Fri 4/23/04 0%
55
Call 4
1 hrMon 4/26/04Mon 4/26/04 0%
56
Call 5
1 hrTue 4/27/04Tue 4/27/04 0%
57
Call 6
1 hrWed 4/28/04Wed 4/28/04 0%
58
Call 7
1 hrThu 4/29/04Thu 4/29/04 0%
59
Call 8
1 hrFri 4/30/04Fri 4/30/04 0%
60
Call 9
1 hrMon 5/3/04Mon 5/3/04 0%
61
Call 10
1 hrTue 5/4/04Tue 5/4/04 0%
62
Collect feedback and compile results
2.5 daysMon 5/3/04Wed 5/5/04 0%
63
Determine need for make up training
1.5 daysWed 5/5/04Thu 5/6/04 0%
64
Update department heads with training results
2 daysWed 5/5/04Fri 5/7/04 0%
65
Issue certificates of completion to participants
1 dayFri 5/7/04Mon 5/10/04 0%
66
Stage 3 - TRIP - End project implementation and control
0 daysMon 5/10/04Mon 5/10/04 0%
67
TRIP - Stage 4 - Project Close Out and Conclusion
108 daysWed 5/12/04Mon 10/11/04 0%
68
Performance measurement through post-training review of deliverables
8 daysWed 5/12/04Mon 5/24/04 0%
69
Discuss evaluations, results, and process improvements with training team support staff
1 dayWed 5/12/04Thu 5/13/04 0%
70
Create a list of best practices and FAQ for future training endeavors
3 daysThu 5/13/04Tue 5/18/04 0%
71
Discuss results with vendor for any improvements
2 daysTue 5/18/04Thu 5/20/04 0%
72
Identify issues that were problems and improve them
2 daysThu 5/20/04Mon 5/24/04 0%
73
Conduct Return On Investment (ROI) Research
10 daysMon 9/27/04Mon 10/11/04 0%
74
Send ROI forms to participants and department heads
2 daysMon 9/27/04Wed 9/29/04 0%
75
Measure ROI according to established parameters
5 daysTue 9/28/04Tue 10/5/04 0%
76
Compile results and present findings to department heads and HR and training managers
4 daysTue 10/5/04Mon 10/11/04 0%
77
Stage 4 - TRIP - End project close out and conclusion
0 daysMon 10/11/04Mon 10/11/04 0%
78
Party!! For training team support staff (and vendor staff)
1 dayMon 5/10/04Tue 5/11/04 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete