| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Training Rollout Initiative and Plan (TRIP) | 157.5 days | Thu 3/4/04 | Mon 10/11/04 | | 0% |
| 2 | TRIP - Stage 1 - Project Planning | 19 days | Thu 3/4/04 | Tue 3/30/04 | | 0% |
| 3 | Define project objectives and describe mission statement | 2 days | Thu 3/4/04 | Fri 3/5/04 | | 0% |
| 4 | Ensure total participation by training team support staff | 1 day | Thu 3/4/04 | Thu 3/4/04 | | 0% |
| 5 | Identify Departments or End-User Community to be Trained | 7 days | Fri 3/5/04 | Mon 3/15/04 | | 0% |
| 6 | Create list of target departments | 1 day | Mon 3/8/04 | Mon 3/8/04 | | 0% |
| 7 | Perform departmental training needs analysis | 7 days | Fri 3/5/04 | Mon 3/15/04 | | 0% |
| 8 | Compile results and present findings to training coordinator | 2 days | Wed 3/10/04 | Thu 3/11/04 | | 0% |
| 9 | Prioritize training delivery according to critical need | 2 days | Fri 3/12/04 | Mon 3/15/04 | | 0% |
| 10 | Inform department heads of the training initiative | 2 days | Tue 3/9/04 | Wed 3/10/04 | | 0% |
| 11 | Determine if training can be done in-house or outsourced | 1.5 days | Tue 3/9/04 | Wed 3/10/04 | | 0% |
| 12 | Seek Input from Training Vendor | 11 days | Wed 3/10/04 | Thu 3/25/04 | | 0% |
| 13 | Define vendor deliverables - can they meet our needs? | 1 day | Wed 3/10/04 | Thu 3/11/04 | | 0% |
| 14 | Obtain vendor commitment to training rollout schedule | 3 days | Thu 3/11/04 | Tue 3/16/04 | | 0% |
| 15 | Review and customize training material | 7 days | Tue 3/16/04 | Thu 3/25/04 | | 0% |
| 16 | Obtain approval for purchase orders to cover vendor invoices | 2 days | Tue 3/16/04 | Thu 3/18/04 | | 0% |
| 17 | Perform End-User Skill Assessment | 11 days | Tue 3/16/04 | Tue 3/30/04 | | 0% |
| 18 | Create a list of training recipients by department | 2 days | Tue 3/16/04 | Wed 3/17/04 | | 0% |
| 19 | Send skill assessment forms to department heads | 2 days | Thu 3/18/04 | Fri 3/19/04 | | 0% |
| 20 | Collect and compile results by department | 5 days | Mon 3/22/04 | Fri 3/26/04 | | 0% |
| 21 | Initiate end-user placement matrix | 3 days | Thu 3/25/04 | Mon 3/29/04 | | 0% |
| 22 | Finalize project budget | 2 days | Mon 3/29/04 | Tue 3/30/04 | | 0% |
| 23 | Stage 1 - TRIP - End project initiation | 0 days | Tue 3/30/04 | Tue 3/30/04 | | 0% |
| 24 | TRIP - Stage 2 - Project Commencement | 14 days | Tue 3/30/04 | Fri 4/16/04 | | 0% |
| 25 | Prepare Rollout Schedule and Create Awareness | 12 days | Tue 3/30/04 | Wed 4/14/04 | | 0% |
| 26 | Determine course dates, start and end times, and locations | 3 days | Tue 3/30/04 | Thu 4/1/04 | | 0% |
| 27 | Post course outlines and schedule on corporate intranet | 1 day | Fri 4/2/04 | Mon 4/5/04 | | 0% |
| 28 | Establish support through help desk for post-training questions | 1 day | Fri 4/2/04 | Fri 4/2/04 | | 0% |
| 29 | Reserve training rooms | 1 day | Fri 4/2/04 | Fri 4/2/04 | | 0% |
| 30 | Coordinate with information technology team for optimal workstation and equipment performance | 1 day | Mon 4/5/04 | Tue 4/6/04 | | 0% |
| 31 | Order training manuals and necessary material | 7 days | Fri 4/2/04 | Mon 4/12/04 | | 0% |
| 32 | Marketing Strategy | 9 days | Fri 4/2/04 | Wed 4/14/04 | | 0% |
| 33 | Order promotional material | 7 days | Fri 4/2/04 | Mon 4/12/04 | | 0% |
| 34 | Create posters and place them in high-traffic areas | 4 days | Fri 4/9/04 | Wed 4/14/04 | | 0% |
| 35 | E-mail invitation to participants | 1 day | Fri 4/9/04 | Fri 4/9/04 | | 0% |
| 36 | Arrange for catering of meals and refreshments | 1 day | Mon 4/12/04 | Mon 4/12/04 | | 0% |
| 37 | Training Sessions Registration | 5 days | Fri 4/9/04 | Thu 4/15/04 | | 0% |
| 38 | Enroll users who registered via corporate intranet | 2 days | Fri 4/9/04 | Mon 4/12/04 | | 0% |
| 39 | Send out confirmations to these registration | 1 day | Tue 4/13/04 | Tue 4/13/04 | | 0% |
| 40 | Send out prework requirements | 2 days | Fri 4/9/04 | Mon 4/12/04 | | 0% |
| 41 | Monitor cancellations and late requests for training | 1 day | Thu 4/15/04 | Thu 4/15/04 | | 0% |
| 42 | Schedule Instructors | 3 days | Mon 4/5/04 | Thu 4/8/04 | | 0% |
| 43 | In-house instructors | 1 day | Mon 4/5/04 | Tue 4/6/04 | | 0% |
| 44 | Outsourced instructors | 3 days | Mon 4/5/04 | Thu 4/8/04 | | 0% |
| 45 | Courseware Evaluations | 3 days | Wed 4/7/04 | Mon 4/12/04 | | 0% |
| 46 | Reuse or build an end-user course evaluation form (online or paper) | 2 days | Wed 4/7/04 | Fri 4/9/04 | | 0% |
| 47 | Reuse or build an special feedback form for instructors | 2 days | Thu 4/8/04 | Mon 4/12/04 | | 0% |
| 48 | Stage 2 - TRIP - End project commencement | 0 days | Fri 4/16/04 | Fri 4/16/04 | | 0% |
| 49 | TRIP - Stage 3 - Project Implementation and Control | 13.5 days | Wed 4/21/04 | Mon 5/10/04 | | 0% |
| 50 | Conduct training and track attendance | 10 days | Wed 4/21/04 | Tue 5/4/04 | | 0% |
| 51 | Daily Conference Call (Hold Daily Call to Address Issues) | 9.25 days | Wed 4/21/04 | Tue 5/4/04 | | 0% |
| 52 | Call 1 | 1 hr | Wed 4/21/04 | Wed 4/21/04 | | 0% |
| 53 | Call 2 | 1 hr | Thu 4/22/04 | Thu 4/22/04 | | 0% |
| 54 | Call 3 | 1 hr | Fri 4/23/04 | Fri 4/23/04 | | 0% |
| 55 | Call 4 | 1 hr | Mon 4/26/04 | Mon 4/26/04 | | 0% |
| 56 | Call 5 | 1 hr | Tue 4/27/04 | Tue 4/27/04 | | 0% |
| 57 | Call 6 | 1 hr | Wed 4/28/04 | Wed 4/28/04 | | 0% |
| 58 | Call 7 | 1 hr | Thu 4/29/04 | Thu 4/29/04 | | 0% |
| 59 | Call 8 | 1 hr | Fri 4/30/04 | Fri 4/30/04 | | 0% |
| 60 | Call 9 | 1 hr | Mon 5/3/04 | Mon 5/3/04 | | 0% |
| 61 | Call 10 | 1 hr | Tue 5/4/04 | Tue 5/4/04 | | 0% |
| 62 | Collect feedback and compile results | 2.5 days | Mon 5/3/04 | Wed 5/5/04 | | 0% |
| 63 | Determine need for make up training | 1.5 days | Wed 5/5/04 | Thu 5/6/04 | | 0% |
| 64 | Update department heads with training results | 2 days | Wed 5/5/04 | Fri 5/7/04 | | 0% |
| 65 | Issue certificates of completion to participants | 1 day | Fri 5/7/04 | Mon 5/10/04 | | 0% |
| 66 | Stage 3 - TRIP - End project implementation and control | 0 days | Mon 5/10/04 | Mon 5/10/04 | | 0% |
| 67 | TRIP - Stage 4 - Project Close Out and Conclusion | 108 days | Wed 5/12/04 | Mon 10/11/04 | | 0% |
| 68 | Performance measurement through post-training review of deliverables | 8 days | Wed 5/12/04 | Mon 5/24/04 | | 0% |
| 69 | Discuss evaluations, results, and process improvements with training team support staff | 1 day | Wed 5/12/04 | Thu 5/13/04 | | 0% |
| 70 | Create a list of best practices and FAQ for future training endeavors | 3 days | Thu 5/13/04 | Tue 5/18/04 | | 0% |
| 71 | Discuss results with vendor for any improvements | 2 days | Tue 5/18/04 | Thu 5/20/04 | | 0% |
| 72 | Identify issues that were problems and improve them | 2 days | Thu 5/20/04 | Mon 5/24/04 | | 0% |
| 73 | Conduct Return On Investment (ROI) Research | 10 days | Mon 9/27/04 | Mon 10/11/04 | | 0% |
| 74 | Send ROI forms to participants and department heads | 2 days | Mon 9/27/04 | Wed 9/29/04 | | 0% |
| 75 | Measure ROI according to established parameters | 5 days | Tue 9/28/04 | Tue 10/5/04 | | 0% |
| 76 | Compile results and present findings to department heads and HR and training managers | 4 days | Tue 10/5/04 | Mon 10/11/04 | | 0% |
| 77 | Stage 4 - TRIP - End project close out and conclusion | 0 days | Mon 10/11/04 | Mon 10/11/04 | | 0% |
| 78 | Party!! For training team support staff (and vendor staff) | 1 day | Mon 5/10/04 | Tue 5/11/04 | | 0% |