| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Infrastructure Deployment Template | 141.25 days | Mon 1/3/00 | Tue 7/18/00 | | 0% |
| 2 | Scope | 4 days | Mon 1/3/00 | Thu 1/6/00 | | 0% |
| 3 | Determine project scope | 1 day | Mon 1/3/00 | Mon 1/3/00 | Project management | 0% |
| 4 | Secure project sponsorship | 1 day | Tue 1/4/00 | Tue 1/4/00 | Project management | 0% |
| 5 | Define preliminary resources | 1 day | Wed 1/5/00 | Wed 1/5/00 | Project management | 0% |
| 6 | Secure core resources | 1 day | Thu 1/6/00 | Thu 1/6/00 | Project management | 0% |
| 7 | Scope complete | 0 days | Thu 1/6/00 | Thu 1/6/00 | | 0% |
| 8 | Analysis | 30 days | Fri 1/7/00 | Thu 2/17/00 | | 0% |
| 9 | Review Current Infrastructure | 5 days | Fri 1/7/00 | Thu 1/13/00 | | 0% |
| 10 | Review hardware environment | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 11 | Review software environment | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 12 | Review communications environment | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 13 | Review connectivity LAN/WAN | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 14 | Review support environment | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 15 | Review geographic factors | 5 days | Fri 1/7/00 | Thu 1/13/00 | Architecture analyst | 0% |
| 16 | Review current infrastructure complete | 0 days | Thu 1/13/00 | Thu 1/13/00 | | 0% |
| 17 | Review business goals/direction/vision | 10 days | Fri 1/14/00 | Thu 1/27/00 | Project management | 0% |
| 18 | Identify Target Areas for Improvement | 5 days | Fri 1/28/00 | Thu 2/3/00 | | 0% |
| 19 | Identify hardware improvements | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 20 | Identify software improvements | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 21 | Identify communications considerations | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 22 | Identify connectivity LAN/WAN improvements/issues | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 23 | Identify support environment improvements/additions | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 24 | Identify mitigation of geographic factors | 5 days | Fri 1/28/00 | Thu 2/3/00 | Architecture analyst | 0% |
| 25 | Identify target areas for improvement | 0 days | Thu 2/3/00 | Thu 2/3/00 | | 0% |
| 26 | Define system requirements | 5 days | Fri 2/4/00 | Thu 2/10/00 | Architecture analyst | 0% |
| 27 | Define target performance metrics | 5 days | Fri 2/11/00 | Thu 2/17/00 | Architecture analyst | 0% |
| 28 | Review Current Market Solution Vendors | 5 days | Fri 2/4/00 | Thu 2/10/00 | | 0% |
| 29 | Hardware vendors | 5 days | Fri 2/4/00 | Thu 2/10/00 | Procurement | 0% |
| 30 | Software vendors | 5 days | Fri 2/4/00 | Thu 2/10/00 | Procurement | 0% |
| 31 | Communications vendors | 5 days | Fri 2/4/00 | Thu 2/10/00 | Procurement | 0% |
| 32 | Design partners | 5 days | Fri 2/4/00 | Thu 2/10/00 | Procurement | 0% |
| 33 | Implementation partners | 5 days | Fri 2/4/00 | Thu 2/10/00 | Procurement | 0% |
| 34 | Review current market solution vendors complete | 0 days | Thu 2/10/00 | Thu 2/10/00 | | 0% |
| 35 | Analysis complete | 0 days | Thu 2/17/00 | Thu 2/17/00 | | 0% |
| 36 | Design | 27 days | Fri 2/18/00 | Mon 3/27/00 | | 0% |
| 37 | Secure necessary architectural resources | 3 days | Fri 2/18/00 | Tue 2/22/00 | Project management | 0% |
| 38 | Draft Preliminary Infrastructure Design Documents | 5 days | Wed 2/23/00 | Tue 2/29/00 | | 0% |
| 39 | Preliminary hardware design | 5 days | Wed 2/23/00 | Tue 2/29/00 | Architecture analyst | 0% |
| 40 | Preliminary software design | 5 days | Wed 2/23/00 | Tue 2/29/00 | Architecture analyst | 0% |
| 41 | Preliminary communications design | 5 days | Wed 2/23/00 | Tue 2/29/00 | Architecture analyst | 0% |
| 42 | Preliminary connectivity LAN/WAN design | 5 days | Wed 2/23/00 | Tue 2/29/00 | Architecture analyst | 0% |
| 43 | Preliminary support environment design | 5 days | Wed 2/23/00 | Tue 2/29/00 | Architecture analyst | 0% |
| 44 | Draft preliminary infrastructure design document complete | 0 days | Tue 2/29/00 | Tue 2/29/00 | | 0% |
| 45 | Review preliminary design documents | 2 days | Wed 3/1/00 | Thu 3/2/00 | Project management,Management | 0% |
| 46 | Obtain feedback/input on design | 2 days | Fri 3/3/00 | Mon 3/6/00 | Project management,Management | 0% |
| 47 | Develop Detailed Infrastructure Design Documents | 5 days | Tue 3/7/00 | Mon 3/13/00 | | 0% |
| 48 | Develop detailed hardware design | 5 days | Tue 3/7/00 | Mon 3/13/00 | Architecture analyst | 0% |
| 49 | Develop detailed software design | 5 days | Tue 3/7/00 | Mon 3/13/00 | Architecture analyst | 0% |
| 50 | Develop detailed communications design | 5 days | Tue 3/7/00 | Mon 3/13/00 | Architecture analyst | 0% |
| 51 | Develop detailed connectivity LAN/WAN design | 5 days | Tue 3/7/00 | Mon 3/13/00 | Architecture analyst | 0% |
| 52 | Develop detailed support environment design | 5 days | Tue 3/7/00 | Mon 3/13/00 | Architecture analyst | 0% |
| 53 | Develop detailed infrastructure design documents complete | 0 days | Mon 3/13/00 | Mon 3/13/00 | | 0% |
| 54 | Align long/short term infrastructure design with business goals | 10 days | Tue 3/14/00 | Mon 3/27/00 | Architecture analyst,Project management | 0% |
| 55 | Design complete | 0 days | Mon 3/27/00 | Mon 3/27/00 | | 0% |
| 56 | Budget | 16 days | Tue 3/28/00 | Tue 4/18/00 | | 0% |
| 57 | Develop budget based on detailed infrastructure documents | 5 days | Tue 3/28/00 | Mon 4/3/00 | Project management | 0% |
| 58 | Align budget request with business goals | 5 days | Thu 3/30/00 | Thu 4/6/00 | Project management | 0% |
| 59 | Align budget request with infrastructure requirements timeline | 5 days | Tue 4/4/00 | Mon 4/10/00 | Project management | 0% |
| 60 | Present long/short term budget request | 3 days | Tue 4/11/00 | Thu 4/13/00 | Project management | 0% |
| 61 | Secure multi-phase/year funding for key initiatives | 3 days | Fri 4/14/00 | Tue 4/18/00 | Project management | 0% |
| 62 | Budget complete | 0 days | Tue 4/18/00 | Tue 4/18/00 | | 0% |
| 63 | Finalization/Validation | 17.5 days | Wed 4/19/00 | Fri 5/12/00 | | 0% |
| 64 | Secure resources based upon approved initiatives | 5 days | Wed 4/19/00 | Tue 4/25/00 | Project management | 0% |
| 65 | Finalize detailed design based upon budgetary considerations | 2 days | Wed 4/26/00 | Thu 4/27/00 | Project management | 0% |
| 66 | Develop detailed implementation strategy | 5 days | Fri 4/28/00 | Thu 5/4/00 | Deployment resources | 0% |
| 67 | Validate implementation strategy in test environment | 3 days | Fri 5/5/00 | Tue 5/9/00 | Deployment resources | 0% |
| 68 | Review implementation strategy noting other initiatives | 2 days | Wed 5/10/00 | Thu 5/11/00 | Deployment resources | 0% |
| 69 | Secure approval to proceed | 4 hrs | Fri 5/12/00 | Fri 5/12/00 | Project management | 0% |
| 70 | Finalization/validation complete | 0 days | Fri 5/12/00 | Fri 5/12/00 | | 0% |
| 71 | Deployment | 43.75 days | Fri 5/12/00 | Thu 7/13/00 | | 0% |
| 72 | Logistics | 8 days | Fri 5/12/00 | Wed 5/24/00 | | 0% |
| 73 | Secure deployment resources | 5 days | Fri 5/12/00 | Fri 5/19/00 | Project management,Deployment resources | 0% |
| 74 | Train deployment resources in deployment methodology | 3 days | Fri 5/19/00 | Wed 5/24/00 | Project management,Deployment resources | 0% |
| 75 | Logistics complete | 0 days | Wed 5/24/00 | Wed 5/24/00 | | 0% |
| 76 | Pilot | 10.5 days | Wed 5/24/00 | Wed 6/7/00 | | 0% |
| 77 | Select infrastructure component to deploy | 1 day | Wed 5/24/00 | Thu 5/25/00 | Project management,Deployment resources | 0% |
| 78 | Review deployment team tasks and timeline | 2 days | Thu 5/25/00 | Mon 5/29/00 | Project management,Deployment resources | 0% |
| 79 | Communicate impact to community | 2 hrs | Mon 5/29/00 | Mon 5/29/00 | Project management,Deployment resources | 0% |
| 80 | Deploy infrastructure component | 3 days | Mon 5/29/00 | Thu 6/1/00 | Project management,Deployment resources | 0% |
| 81 | Test infrastructure component | 1 day | Thu 6/1/00 | Fri 6/2/00 | Project management,Deployment resources | 0% |
| 82 | Release to production/operations environment | 2 hrs | Fri 6/2/00 | Fri 6/2/00 | Project management,Deployment resources | 0% |
| 83 | Obtain feedback | 2 days | Mon 6/5/00 | Tue 6/6/00 | Project management,Deployment resources | 0% |
| 84 | Evaluate pilot feedback | 1 day | Wed 6/7/00 | Wed 6/7/00 | Project management,Deployment resources | 0% |
| 85 | Pilot complete | 0 days | Wed 6/7/00 | Wed 6/7/00 | | 0% |
| 86 | Determine readiness to proceed | 1 day | Thu 6/8/00 | Thu 6/8/00 | Project management,Management | 0% |
| 87 | Final Deployment | 24.25 days | Fri 6/9/00 | Thu 7/13/00 | | 0% |
| 88 | Review deployment team tasks and timeline | 5 days | Fri 6/9/00 | Thu 6/15/00 | Deployment resources | 0% |
| 89 | Communicate impact to community | 2 hrs | Fri 6/16/00 | Fri 6/16/00 | Deployment resources | 0% |
| 90 | Deploy infrastructure components | 10 days | Fri 6/16/00 | Fri 6/30/00 | Deployment resources | 0% |
| 91 | Test infrastructure component | 5 days | Fri 6/30/00 | Fri 7/7/00 | Deployment resources | 0% |
| 92 | Release to production/operations environment | 1 day | Fri 7/7/00 | Mon 7/10/00 | Deployment resources | 0% |
| 93 | Obtain feedback | 3 days | Mon 7/10/00 | Thu 7/13/00 | Deployment resources | 0% |
| 94 | Final deployment complete | 0 days | Thu 7/13/00 | Thu 7/13/00 | | 0% |
| 95 | Post Implementation Review | 3 days | Thu 7/13/00 | Tue 7/18/00 | | 0% |
| 96 | Document lessons learned | 1 day | Thu 7/13/00 | Fri 7/14/00 | Architecture analyst,Project management,Deployment resources | 0% |
| 97 | Distribute to team members | 1 day | Fri 7/14/00 | Mon 7/17/00 | Architecture analyst,Project management,Deployment resources | 0% |
| 98 | Create software maintenance team | 1 day | Mon 7/17/00 | Tue 7/18/00 | Architecture analyst,Project management,Deployment resources | 0% |
| 99 | Post implementation review complete | 0 days | Tue 7/18/00 | Tue 7/18/00 | | 0% |
| 100 | Infrastructure deployment template complete | 0 days | Tue 7/18/00 | Tue 7/18/00 | | 0% |